State Route 210/215 Connectors |
Description: In San Bernardino, on SR 210 and I-215, from northbound I-215 to westbound SR 210 and from eastbound SR 210 to southbound I-215. Construct direct connectors.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | San Bernardino |
Zip Code | 92405, 92407, 92411 |
Senate District |
32 |
Assembly District | 62, 63 |
Congressional District | 43 |
Caltrans District |
08 |
County/State Route | San Bernardino 215 |
Postmile Begin/End | 9 11.6 |
County/State Route | San Bernardino 210 |
Postmile Begin/End | 21.8 22.1 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 0.75 | |
Daily Travel Time Savings (hours) | 2886 | 2363 |
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | 3.5 | 2 |
Peak Period Time Savings (minutes) | 343200 | 172480 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Design (PS&E) Phase |
San Bernardino Associated Governments | Garry Cohoe | (909) 884-8276 | gcohoe@sanbag.ca.gov | |
Right of Way Phase |
Caltrans | Robert So | (909) 383-4513 | robert_so@dot.ca.gov | |
Construction Phase |
Caltrans | Robert So | (909) 383-4513 | robert_so@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | John Pagano | (909) 383-6327 | john_pagano@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $31,005 | $31,005 | ||||
CMIA |
$81,000 | $-19,586 | $61,414 | ||||
Non-bond Funding | |||||||
State/Federal* |
$69,738 | $-57,487 | $12,251 | ||||
Local** |
$10,341 | $3,261 | $13,602 | ||||
Total**** | $161,079 | $-42,807 | $118,272 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,800 | $0 | $1,800 | $53 | |||
Design(PS&E) |
$8,541 | $1,390 | $9,931 | $1,677 | |||
Right of Way |
$11,771 | $1,801 | $13,572 | $10,023 | |||
Construction |
$138,967 | $-45,998 | $92,969 | $84,372 | |||
Total* | $161,079 | $-42,807 | $118,272 | $96,125 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
12/01/1987 07/01/2007 |
|
12/01/1987 07/01/2007 |
100 | 02/02/1987 07/24/2007 |
10 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2006 02/01/2009 |
|
01/01/2006 05/01/2009 |
100 | 01/01/2006 05/15/2009 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2007 11/01/2008 |
|
07/01/2007 11/01/2008 |
100 | 07/20/2006 11/01/2008 |
12 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2009 10/01/2011 |
|
08/01/2009 02/01/2013 |
100 | 09/17/2009 03/01/2013 |
-2 -1 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2011 11/01/2012 |
|
02/01/2013 03/01/2015 |
0 | 05/01/2014 11/16/2015 |
-15 -9 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2008 | 06/01/2008 | 95 | 07/01/2011 | -37 | ||
Implementation Date | 09/01/2008 | 09/01/2008 | 0 | 08/01/2011 | -35 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 0.75 | |
Daily Travel Time Savings (hours) | 2886 | 2363 |
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | 3.5 | 2 |
Peak Period Time Savings (minutes) | 343200 | 172480 |
Bond Funding Cost | |
---|---|
Adopted: |
$22,000,000 |
Current Approved: |
$29,000,000 |
Actual Expenditures: |
$26,514,000 |
Status as of December 31, 2023.