State Route 210/215 Connectors

Description: In San Bernardino, on SR 210 and I-215, from northbound I-215 to westbound SR 210 and from eastbound SR 210 to southbound I-215. Construct direct connectors.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92405, 92407, 92411
 
Senate District
32
Assembly District 62, 63
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 215
Postmile Begin/End 9 11.6
 
County/State Route San Bernardino 210
Postmile Begin/End 21.8 22.1
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  0.75      
Daily Travel Time Savings (hours)  2886    2363  
Lane Miles Added (HOV)      2  
Lane Miles Added (Mixed)  3.5    2  
Peak Period Time Savings (minutes)  343200    172480  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Bernardino Associated Governments Garry Cohoe (909) 884-8276   gcohoe@sanbag.ca.gov
Design (PS&E) Phase
San Bernardino Associated Governments Garry Cohoe (909) 884-8276   gcohoe@sanbag.ca.gov
Right of Way Phase
Caltrans Robert So (909) 383-4513   robert_so@dot.ca.gov
Construction Phase
Caltrans Robert So (909) 383-4513   robert_so@dot.ca.gov
 
Corridor System Management Plan
Caltrans John Pagano (909) 383-6327   john_pagano@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $31,005 $31,005
CMIA
$81,000 $-19,586 $61,414
Non-bond Funding
State/Federal*
$69,738 $-57,487 $12,251
Local**
$10,341 $3,261 $13,602
 
Total**** $161,079 $-42,807 $118,272

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,800 $0 $1,800 $53
Design(PS&E)
$8,541 $1,390 $9,931 $1,677
Right of Way
$11,771 $1,801 $13,572 $10,023
Construction
$138,967 $-45,998 $92,969 $84,372
 
Total* $161,079 $-42,807 $118,272 $96,125

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/1987 

07/01/2007 
 

 
12/01/1987 

07/01/2007 
100  02/02/1987 

07/24/2007 
10 

-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2006 

02/01/2009 
 

 
01/01/2006 

05/01/2009 
100  01/01/2006 

05/15/2009 


Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

11/01/2008 
 

 
07/01/2007 

11/01/2008 
100  07/20/2006 

11/01/2008 
12 

Begin Construction Phase

End Construction Phase
06/01/2009 

10/01/2011 
 

 
08/01/2009 

02/01/2013 
100  09/17/2009 

03/01/2013 
-2 

-1 
Begin Closeout Phase

End Closeout Phase
11/01/2011 

11/01/2012 
 

 
02/01/2013 

03/01/2015 
05/01/2014 

11/16/2015 
-15 

-9 
Corridor System Management Plan
Adoption Date 06/01/2008    06/01/2008  95  07/01/2011  -37 
Implementation Date 09/01/2008    09/01/2008  08/01/2011  -35 
????????
Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 0.75
Daily Travel Time Savings (hours) 2886 2363
Lane Miles Added (HOV) 2
Lane Miles Added (Mixed) 3.5 2
Peak Period Time Savings (minutes) 343200 172480

Bond Funding Cost
Adopted:
$22,000,000
Current Approved:
$29,000,000
Actual Expenditures:
$26,514,000

 

Status as of December 31, 2023.